GCI Cable Laying Barge Schedule Updated

There was an updated barge laying schedule sent on July 3rd.  The schedule has slipped by a few days due to unavailable accomadation unit for the barge crew.   The new schedule has the barge arriving in Ketchikan July 16th and commencing the installation on the 18th.  The barge will lay cable to Wrangell and conduct the Wrangell landing on 7/21-22/08 followed by installation to South Mitkof 7/24/08 and then to Petersburg with the landing there on 7/26/08.  The installation will continue on towards Juneau and then start down Chatham Straits to Sitka.  We will update the page as we get new information and corrections to the schedule.